Constructive Thinking Logo

Steel Frame Erected

April 2nd 2015

A couple of weeks ago, Jon and I went down to Worcester at a completely uncivilised time of day in order to watch the key parts of the steel frame, previously featured in the fabricators yard, being erected on site. You can see the existing roof has been retained, the external walls have been built up locally and had pad stones fitted to accept the columns. Given the way we work we were 99% sure, but you can never really be certain until it turns up on site.